Major turnaround and revamp of the Cat Cracker 2

Definition:

Major turnaround and revamp of the Cat Cracker 2 and Gas Plant 3 facilities at Shell Netherlands Raffinaderijen in Pernis. Apart from regular maintenance and inspection, major equipment replacement was a feature of this project.

Project execution phase:

Preparation throughout 2001, shutdown in April 2002.

Major turnaround and revamp of the cat cracker in Pernis

Stork’s role in the project:

Stork was construction contractor (mechanical), carrying out 190.000 man hours for Stork, 110.000 man hours for subcontractors and a peak of 650 men.

Stork Industry Services was also construction contractor on the 2006 Cat Cracker Turnaround and Jacobs life time extension project.